Progress
 
 
Project Details
DAR-2018-000060
BPR/Impvt.of IVR Panthoibi Keinou/3
Impvt.of IVR Panthoibi Keinou Thongkha Makha Leirak from NH-150 to Samairou Taba at Keinou(SH:Widening, banking, GSB, WBM & PC.
2018-01-06
PWD
Bishnupur
100.00
0.00
Central Sector
Completed
2nd phase
24.67266434439012,93.78617551108437
Progress Update : 2018-10-10
Completed
2nd phase
se3pwd
24.67266434439012,93.78617551108437
24.6712932,93.7890184
0.32519539840951
Approved
2018-10-16 09:53:53
se3pwd
0
R/R Drain,Road work(GSB,WBM,PC),E/W in banking & widening

Progress Update : 2018-10-10
Completed
2nd phase
se3pwd
24.67266434439012,93.78617551108437
24.6716872,93.7884431
0.25357108770938
Approved
2018-10-16 09:55:06
se3pwd
0
R/R Drain,Road work(GSB,WBM,PC),E/W in banking & widening

Progress Update : 2018-10-10
Completed
2nd phase
se3pwd
24.67266434439012,93.78617551108437
24.6716914,93.7884614
0.2550445479446
Approved
2018-10-16 09:54:38
se3pwd
0
R/R Drain,Road work(GSB,WBM,PC),E/W in banking & widening

Progress Update : 2018-10-07
Completed
2nd
se3pwd
24.67266434439012,93.78617551108437
24.6444943,93.7697702
3.5438596118045
Approved
2018-10-16 09:55:55
se3pwd
0
Repairing of bridge at Ngachroupokpi high canal

Foundation & Inauguration
-
-
-

-
-
-