Project Details
DAR-2023-000091
CB@SENAPATI
Construction of District Court Building at Senapati
05/04/2021
Law & Legislative Affairs Department
Senapati
100000000.00
450
Manipur Tribal Development Corporation Ltd
State Plan
55%
1
25.272760, 94.02425
District Court Building, RCC Frame G+1 Structure containing 3 Nos. of Court Rooms with supporting staff room and supporting spaces.
Progress Update : 30/07/2024
55%
1
Mtdc_Law
25.272760, 94.02425
25.2730297,94.0237166
0.061446220737497
450
work is in progress

Progress Update : 19/02/2023
45% Completed
Phase of
Mtdc_Law
25.272760, 94.02425
25.27278548,94.02406232
0.019082257533766
0
First Floor slab completed and first Floor column in progress

Progress Update : 19/02/2023
45% Completed
Phase of
Mtdc_Law
25.272760, 94.02425
25.27292719,94.02419022
0.01953728864528
30000000
First Floor slab completed and first Floor column in progress