Progress
 
 
Project Details
DAR-2018-000047
WP-16/17-POLY-TAKYEL
Improvement of infrastructure for Government Polytechnic, Takyel, Imphal
21/11/2016
Education (S)
Imphal-West
76.00
46.74
State Plan
Completed
Nil
24.79939888273165,93.90441389570083
Improvement of infrastructure for Government Polytechnic, Takyel, Imphal
Progress Update : 19/06/2018
Completed
Nil
sur1.eew-mn
24.79939888273165,93.90441389570083
24.7993033,93.9047417
0.034752168399813
0
Side view (Water reservoir)

Progress Update : 19/06/2018
Completed
Nil
sur1.eew-mn
24.79939888273165,93.90441389570083
24.7996099,93.9053522
0.097571520946609
0
Front view (Water reservoir)

Progress Update : 11/06/2018
Completed
Nil
sur1.eew-mn
24.79939888273165,93.90441389570083
24.7970033,93.904515
0.26655923698067
0
Side view (water reservoir)

Progress Update : 11/06/2018
Completed
Nil
sur1.eew-mn
24.79939888273165,93.90441389570083
24.7977032,93.9043448
0.18867121478896
0
Front view(water reservoir)

Progress Update : 12/01/2018
Final(Toilet) G+1
Nil
sur1.eew-mn
24.79939888273165,93.90441389570083
24.7991444,93.904836
0.051145731650551
0
Internal

Progress Update : 12/01/2018
Final(Toilet)
Nil
sur1.eew-mn
24.79939888273165,93.90441389570083
24.7991444,93.904836
0.051145731650551
0
Internal