Progress
 
 
Project Details
DAR-2022-001381
RMSA/D-2-AbdulAli Lab- TBL
Infrastructure Development of School under RMSA 2021-22 at Abdul Ali High Madrassa, Thoubal, Manipur.
06/01/2022
Education (S)
Thoubal
30.17
12.06
Under Construction
nill
24.71996087722259,93.94154790043801
Infrastructure Development of School under RMSA 2021-22 at Abdul Ali High Madrassa, Thoubal, Manipur. (Sh: Construction of 1(one) Chemistry Lab, Sh: Construction of 1(one) Science Lab)
Progress Update : 05/01/2024
Under Construction
nill
so7.eew
24.71996087722259,93.94154790043801
24.7203379,93.9412791
0.049944301475183
0
Front View, Science

Progress Update : 05/01/2024
Under Construction
nill
so7.eew
24.71996087722259,93.94154790043801
24.7203568,93.9413472
0.048465275856284
0
Interior View, Science

Progress Update : 05/01/2024
Under Construction
nill
so7.eew
24.71996087722259,93.94154790043801
24.7199526,93.9414585
0.0090761920631073
0
Front View, Chemistry

Progress Update : 05/01/2024
Under Construction
nill
so7.eew
24.71996087722259,93.94154790043801
24.7185468,93.9417821
0.15900004709621
0
Interior View, Chemistry

Progress Update : 30/12/2022
Under Construction
nill
so7.eew
24.71996087722259,93.94154790043801
24.7202638,93.9415854
0.033894259256536
0
Interior View, Science Lab

Progress Update : 30/12/2022
Under Construction
nill
so7.eew
24.71996087722259,93.94154790043801
24.7202705,93.941572
0.034512902342526
0
Front View, Science Lab

Progress Update : 30/12/2022
Under Construction
nill
so7.eew
24.71996087722259,93.94154790043801
24.7201376,93.9416362
0.021578947396996
0
Front View, Chemistry Lab

Progress Update : 30/12/2022
Under Construction
nill
so7.eew
24.71996087722259,93.94154790043801
24.7189339,93.9411449
0.12122676592586
0
Interior View, chemistry Lab