Project Details
DAR-2022-001330
TML/In & around Tamenglong HQ/54
Impvt. of in and around Tamenglong HQ Road - 6.00 Km
23/06/2022
PWD
Tamenglong
200.04
0.00
CSS / CPS
In progress
1
24.99126968647795,93.50018971366116
WBM Grade-III on selected stretches & 2 cm Premix Carpet with Seal Coat
Progress Update : 16/01/2023
In progress
1
eetmld
24.99126968647795,93.50018971366116
24.9903722,93.5008136
0.1179471827119
0
Completed - BT Surface

Progress Update : 16/01/2023
In progress
1
eetmld
24.99126968647795,93.50018971366116
24.9901964,93.5008606
0.13716032035305
0
Completed - BT Surface 0.03 Km

Progress Update : 16/01/2023
In progress
1
eetmld
24.99126968647795,93.50018971366116
24.9902567,93.5008526
0.13095528261088
0
Completed - BT Surface (0.3 Km)

Progress Update : 16/01/2023
In progress
1
eetmld
24.99126968647795,93.50018971366116
24.9882928,93.5015664
0.35890079023816
0
Completed - BT surface (0-3 Km)

Progress Update : 16/01/2023
In progress
1
eetmld
24.99126968647795,93.50018971366116
24.9885733,93.5024883
0.3788783097761
0
WBM Layer