Progress
 
 
Project Details
DAR-2022-001220
EE/ED-III/KPI/Geljang/2017-18
Construction of TD Block complex at Kangchup geljang(SH: Providing IEI in the BDO office and type IV Qtr one number including Yard Lighting)
2018-03-21
PWD
Kangpokpi
299.99
0.00
State Plan
Complete
Complete
24.8696375,93.806072
Installation of Electrical components like MCB, Power Plug, Switch Board,bulb, etc...in TD Block Complex at Kangchup, Geljang
Progress Update : 2022-10-21
Complete
Complete
AE2ED3
24.8696375,93.806072
24.8567203,93.8116333
1.5419498309896
Approved
2022-10-26 07:32:29
seelect
0
Power plug

Progress Update : 2022-10-21
Complete
Complete
AE2ED3
24.8696375,93.806072
24.8567203,93.8116333
1.5419498309896
Approved
2022-10-26 07:32:52
seelect
0
MCB DB for quater

Progress Update : 2022-10-21
Complete
Complete
AE2ED3
24.8696375,93.806072
24.8567203,93.8116333
1.5419498309896
Approved
2022-10-26 07:33:03
seelect
0
Kitkat

Progress Update : 2022-10-21
Complete
Complete
AE2ED3
24.8696375,93.806072
24.8567203,93.8116333
1.5419498309896
Approved
2022-10-26 07:33:14
seelect
0
Switches

Progress Update : 2022-10-21
Complete
Complete
AE2ED3
24.8696375,93.806072
24.8567203,93.8116333
1.5419498309896
Approved
2022-10-26 07:33:27
seelect
0
MCB DB

Progress Update : 2022-10-21
Complete
Complete
AE2ED3
24.8696375,93.806072
24.8567203,93.8116333
1.5419498309896
Approved
2022-10-26 07:33:42
seelect
0
Fan

Progress Update : 2022-10-21
Complete
Complete
AE2ED3
24.8696375,93.806072
24.88039,93.8090933
1.233800412731
Approved
2022-10-26 07:33:50
seelect
0
Power plugs

Progress Update : 2022-10-21
Complete
Complete
AE2ED3
24.8696375,93.806072
24.88039,93.8090933
1.233800412731
Approved
2022-10-26 07:34:01
seelect
0
Sdo office room

Progress Update : 2022-10-21
Complete
Complete
AE2ED3
24.8696375,93.806072
24.88039,93.8090933
1.233800412731
Approved
2022-10-26 07:34:13
seelect
0
Switches

Progress Update : 2022-10-21
Complete
Complete
AE2ED3
24.8696375,93.806072
24.8567203,93.8116333
1.5419498309896
Approved
2022-10-26 07:34:44
seelect
0
Room 1

Progress Update : 2022-10-21
Complete
Complete
AE2ED3
24.8696375,93.806072
24.8567203,93.8116333
1.5419498309896
Approved
2022-10-26 07:35:03
seelect
0
Corridor 2

Progress Update : 2022-10-21
Complete
Complete
AE2ED3
24.8696375,93.806072
24.8567203,93.8116333
1.5419498309896
Approved
2022-10-26 07:36:28
seelect
0
Corridor sdo office

Progress Update : 2022-10-21
Complete
Complete
AE2ED3
24.8696375,93.806072
24.8567203,93.8116333
1.5419498309896
Approved
2022-10-26 07:35:31
seelect
0
Main distribution panel

Foundation & Inauguration
-
-
-

-
-
-