Progress
 
 
Project Details
DAR-2022-001199
UKL_NDB_UKHRUL
Water Supply Scheme at Ukhrul
2021-07-15
PHED
Ukhrul
2452.00
0.00
EAP
Work in progress
Phase I
25.0979645,94.3615964
Progress Update : 2023-02-17
Work in progress
Phase I
ningchui
25.0979645,94.3615964
25.0964393,94.3622587
0.18222754279882
Approved
2023-02-17 08:07:52
eeuklphed
0
Zonal reservoir at Harkui kathe

Progress Update : 2023-02-17
Work in progress
Phase I
ningchui
25.0979645,94.3615964
25.0934246,94.3717696
1.1419955651536
Approved
2023-02-17 08:08:06
eeuklphed
0
Zonal reservoir at Harkui kathe

Progress Update : 2023-02-17
Work in progress
Phase I
ningchui
25.0979645,94.3615964
25.0957339,94.3652182
0.44103380972273
Approved
2023-02-17 08:08:49
eeuklphed
0
Zonal reservoir at Harfarm

Progress Update : 2023-02-17
Work in progress
Phase I
ningchui
25.0979645,94.3615964
25.0957758,94.3672724
0.62118510932811
Approved
2023-02-17 08:09:00
eeuklphed
0
Zonal reservoir at Harfarm

Progress Update : 2023-02-17
Work in progress
Phase I
ningchui
25.0979645,94.3615964
25.0943506,94.3605822
0.41460200766955
Approved
2023-02-17 08:09:12
eeuklphed
0
Zonal reservoir at Seipet

Progress Update : 2023-02-17
Work in progress
Phase I
ningchui
25.0979645,94.3615964
25.0958889,94.363418
0.29479668071891
Approved
2023-02-17 07:49:53
eeuklphed
0
Zonal reservoir at Seipet

Progress Update : 2023-02-17
Work in progress
Phase I
ningchui
25.0979645,94.3615964
25.0978262,94.3605658
0.10490588822079
Approved
2023-02-17 07:51:26
eeuklphed
0
Zonal reservoir at Mini Sectt

Progress Update : 2023-02-17
Work in progress
Phase I
ningchui
25.0979645,94.3615964
25.0928226,94.3596869
0.60319128144437
Approved
2023-02-17 07:53:05
eeuklphed
0
Zonal reservoir at Mini Sectt

Progress Update : 2023-02-17
Work in progress
Phase I
ningchui
25.0979645,94.3615964
25.1016527,94.36135
0.41083921041768
Approved
2023-02-17 07:59:59
eeuklphed
0
Zonal reservoir at Viewland Z IV

Progress Update : 2023-02-17
Work in progress
Phase I
ningchui
25.0979645,94.3615964
25.101662,94.361349
0.41187747380123
Approved
2023-02-17 08:02:53
eeuklphed
0
Zonal reservoir at Viewland Z IV

Progress Update : 2023-02-17
Work in progress
Phase I
ningchui
25.0979645,94.3615964
25.1129689,94.3611698
1.6688857172261
Approved
2023-02-17 08:05:06
eeuklphed
0
Zonal reservoir

Progress Update : 2023-02-17
Work in progress
Phase I
ningchui
25.0979645,94.3615964
25.1129689,94.3611698
1.6688857172261
Approved
2023-02-17 08:07:41
eeuklphed
0
Zonal reservoir

Foundation & Inauguration
-
-
-

-
-
-