Progress
 
 
Project Details
DAR-2018-000020
TAH/TST*
Construction of Girls Hostel at Tadubi, Senapati District
10/06/2010
TA and Hills
Senapati
255.00
127.52
MDS
Central Sector
Under Construction
2nd Installment
25.4789856,94.13474410000003
The estimate provide R.C.C. footing, isolated & combined R.C.C. column, grade beam, lintel, R.C.C. slab, Brick work, 40 mm C.C. flooring, Teak wood in doors, windows, Ventilators, 12 mm cement plaster, finishing with cement paint outside walls, Tubular Truss with GCI sheet roofing.
Progress Update : 05/01/2018
Under Construction
2nd Installment
tahmobileapp
25.4789856,94.13474410000003
25.4791755,94.139948
0.52277088889751
127.5
The estimate provide R.C.C. footing, isolated & combined R.C.C. column, grade beam, lintel, R.C.C. slab, Brick work, 40 mm C.C. flooring, Teak wood in doors, windows, Ventilators, 12 mm cement plaster, finishing with cement paint outside walls, Tubular Truss with GCI sheet roofing. Gunakan ctrl + gulir untuk memperbesar atau memperkecil peta

Progress Update : 05/01/2018
Under Construction
2nd Installment
tahmobileapp
25.4789856,94.13474410000003
25.4791755,94.139948
0.52277088889751
127.52
The estimate provide R.C.C. footing, isolated & combined R.C.C. column, grade beam, lintel, R.C.C. slab, Brick work, 40 mm C.C. flooring, Teak wood in doors, windows, Ventilators, 12 mm cement plaster, finishing with cement paint outside walls, Tubular Truss with GCI sheet roofing. Gunakan ctrl + gulir untuk memperbesar atau memperkecil peta