Progress
 
 
Project Details
DAR-2022-001131
SHD/DAR/2022-23/Rd2/003
Impvt of approach road of Kangchup Geljang SDO/BDO Office
23/06/2022
PWD
Kangpokpi
30.00
0.00
State Plan
Completed
2022-23
24.869077,93.803175
GSB, WBM and PC & SC Pucca Drain, 900 mm Pipe Culvert and Boulder Sausage
Progress Update : 17/01/2023
Completed
2022-23
Sadarhills
24.869077,93.803175
24.86961,93.80331
0.060808598041414
0
Shingling, WBM, PC, Pucca drain, NP-3 Pipe Culvert and boulder sausage

Progress Update : 17/01/2023
Completed
2022-23
Sadarhills
24.869077,93.803175
24.869257,93.8031892
0.020065221772156
0
Shingling, WBM, PC, Pucca drain, NP-3 Pipe Culvert and boulder sausage

Progress Update : 17/01/2023
Completed
2022-23
Sadarhills
24.869077,93.803175
24.8683033,93.8025733
0.10528579832795
0
Shingling, WBM, PC, Pucca drain, NP-3 Pipe Culvert and boulder sausage

Progress Update : 10/10/2022
100%
2022-23
Sadarhills
24.869077,93.803175
24.8672103,93.8068664
0.42632486380566
0
Shingling, WBM, PC, Pucca Drain, NP-3 pipe culvert and boulder sausage