Progress
 
 
Project Details
DAR-2022-001121
EE/ED-I/DM-8/2022
Constn. Of Extension room of Prof. Qtr. No. 8(A& B) at DMC Campus. (S.H.-Providing of IEI in the extension room of Professor Quarter / No. 8(A&B) at D
06/03/2019
PWD
Imphal-West
5451375.00
0.00
2261/05/053/01/02/27
Completed
I
24.819249098771735,93.94154119491591
WIRING EXHAUST FAN FAN TUBES BULB MCB ETC
Progress Update : 20/09/2022
Completed
I
9612165466
24.819249098771735,93.94154119491591
24.8168228,93.941651
0.27000662920442
0
Bed Room2

Progress Update : 20/09/2022
Completed
I
9612165466
24.819249098771735,93.94154119491591
24.8167821,93.94179
0.27545140757222
0
Ceiling fan

Progress Update : 20/09/2022
Completed
I
9612165466
24.819249098771735,93.94154119491591
24.8168599,93.9417768
0.26671599254824
0
Bulb

Progress Update : 20/09/2022
Completed
I
9612165466
24.819249098771735,93.94154119491591
24.8168599,93.9417768
0.26671599254824
0
Power Point

Progress Update : 20/09/2022
Completed
I
9612165466
24.819249098771735,93.94154119491591
24.8168626,93.9417847
0.26648931279616
0
Light/Power Point

Progress Update : 20/09/2022
Completed
I
9612165466
24.819249098771735,93.94154119491591
24.8168642,93.9417894
0.26635634537241
0
Bed Room1

Progress Update : 20/09/2022
Completed
I
9612165466
24.819249098771735,93.94154119491591
24.8168642,93.9417894
0.26635634537241
0
Main Switch