Progress
 
 
Project Details
DAR-2018-000006
IWD/Maklang Road/7
Impvt. of Maklang Road from NH-53 upto Longa Koireng
20/03/2016
PWD
Imphal-West
519.00
100.00
State Plan
Completed
Phase 1
24.79910124115942,93.87553351361089
GSB, WBM & PC
Progress Update : 03/01/2018
Completed
Phase 1
thengra
24.79910124115942,93.87553351361089
24.8087265,93.8119106
6.5101727410329
0
GSB,WBM,pc

Progress Update : 03/01/2018
Completed
Phase 1
thengra
24.79910124115942,93.87553351361089
24.8087254,93.8118814
6.5130598139623
0
GSB,WBM,pc

Progress Update : 03/01/2018
Completed
Phase 1
thengra
24.79910124115942,93.87553351361089
24.8058483,93.7925599
8.40834094844
0
GSB,WBM,pc

Progress Update : 03/01/2018
Completed
Phase 1
thengra
24.79910124115942,93.87553351361089
24.8045912,93.7859311
9.0644972539235
0
GSB,WBM,pc