Progress
 
 
Project Details
DAR-2022-000909
Taningjam Pt-1 P. S SMDC 2022-23
New Primary School (N.P.S)
29/06/2020
Edu (S) - SSA & RMSA
Tamenglong
29.36
19.79
CSS / CPS
Completed
Completed
25.126158333333,93.461966666667
Construction of New Primary School (NPS) at Taningjam Pt-1 P.S has been completed.
Progress Update : 15/09/2022
Completed
Completed
ssatmlnoney
25.126158333333,93.461966666667
25.12613,93.462423333333
0.046079752104313
0
Construction of New Primary School (NPS) at Taningjam PT-1 PS has been completed

Progress Update : 15/09/2022
Completed
Completed
ssatmlnoney
25.126158333333,93.461966666667
25.126138333333,93.462411666667
0.044852635446687
0
Construction of New Primary School (NPS) at Taningjam PT-1 PS has been completed

Progress Update : 15/09/2022
Completed
Completed
ssatmlnoney
25.126158333333,93.461966666667
25.126213333333,93.46253
0.057038598388938
0
Construction of New Primary School (NPS) at Taningjam PT-1 PS has been completed

Progress Update : 15/09/2022
Completed
Completed
ssatmlnoney
25.126158333333,93.461966666667
25.126073333333,93.462141666667
0.019992105331734
0
Construction of New Primary School (NPS) at Taningjam PT-1 PS has been completed

Progress Update : 15/09/2022
Completed
Completed
ssatmlnoney
25.126158333333,93.461966666667
25.12603,93.462148333333
0.023196339063494
0
Construction of New Primary School (NPS) at Taningjam PT-1 PS has been completed

Progress Update : 30/08/2022
Completed
Completed
ssatmlnoney
25.126158333333,93.461966666667
25.126206666667,93.462251666667
0.029189463053607
0
Construction of New Primary School (NPS) at Taningjam PT-1 PS has been completed

Progress Update : 30/08/2022
Completed
Completed
ssatmlnoney
25.126158333333,93.461966666667
25.126313333333,93.462278333333
0.035796942289958
0
Construction of New Primary School (NPS) at Taningjam PT-1 PS has been completed

Progress Update : 30/08/2022
Completed
Completed
ssatmlnoney
25.126158333333,93.461966666667
25.125811666667,93.462518333333
0.067601412336309
0
Construction of New Primary School at Taningjam PT-1 PS has been completed