Progress
 
 
Project Details
DAR-2022-000821
EE-ED-3/BISHNUPUR COURT/1
Construction of G+2 Annexes building for the court of District & Session Judge at Bishnupur-Annexture- C1,C2,C3,C4 .
16/02/2016
PWD
Bishnupur
1042.46
896.80
8443-Civil Deposit
Conpleted
1
24.618311056730775,93.76162934303298
IEI and Electromechanical works - lift,AC,DG Set
Progress Update : 26/06/2022
Conpleted
1
AE2ED3
24.618311056730775,93.76162934303298
24.6182352,93.7615936
0.0091764190519848
0
Lightning arrestor

Progress Update : 26/06/2022
Conpleted
1
AE2ED3
24.618311056730775,93.76162934303298
24.6186696,93.7614443
0.044036093356948
0
Lift machine room 2

Progress Update : 26/06/2022
Conpleted
1
AE2ED3
24.618311056730775,93.76162934303298
24.6186696,93.7614443
0.044036093356948
0
Lift machine room 1

Progress Update : 26/06/2022
Conpleted
1
AE2ED3
24.618311056730775,93.76162934303298
24.6171794,93.7617618
0.12653878249686
0
Court room 2nd floor

Progress Update : 26/06/2022
Conpleted
1
AE2ED3
24.618311056730775,93.76162934303298
24.6171794,93.7617618
0.12653878249686
0
Judge room geyser

Progress Update : 26/06/2022
Conpleted
1
AE2ED3
24.618311056730775,93.76162934303298
24.6171794,93.7617618
0.12653878249686
0
CCTV camera NVR and monitor

Progress Update : 26/06/2022
Conpleted
1
AE2ED3
24.618311056730775,93.76162934303298
24.6171794,93.7617618
0.12653878249686
0
Court room power socket

Progress Update : 26/06/2022
Conpleted
1
AE2ED3
24.618311056730775,93.76162934303298
24.6171794,93.7617618
0.12653878249686
0
Court Room switch socket

Progress Update : 26/06/2022
Conpleted
1
AE2ED3
24.618311056730775,93.76162934303298
24.6171794,93.7617618
0.12653878249686
0
Court Room lighting

Progress Update : 26/06/2022
Conpleted
1
AE2ED3
24.618311056730775,93.76162934303298
24.6171794,93.7617618
0.12653878249686
0
POE switch

Progress Update : 26/06/2022
Conpleted
1
AE2ED3
24.618311056730775,93.76162934303298
24.6171794,93.7617618
0.12653878249686
0
BAR room

Progress Update : 26/06/2022
Conpleted
1
AE2ED3
24.618311056730775,93.76162934303298
24.6171794,93.7617618
0.12653878249686
0
AC indoor unit

Progress Update : 26/06/2022
Conpleted
1
AE2ED3
24.618311056730775,93.76162934303298
24.613095,93.7620793
0.58175193754381
0
CCTV camera

Progress Update : 26/06/2022
Conpleted
1
AE2ED3
24.618311056730775,93.76162934303298
24.6171794,93.7617618
0.12653878249686
0
Exhaust fan toilet

Progress Update : 26/06/2022
Conpleted
1
AE2ED3
24.618311056730775,93.76162934303298
24.613095,93.7620793
0.58175193754381
0
Server room rack

Progress Update : 26/06/2022
Conpleted
1
AE2ED3
24.618311056730775,93.76162934303298
24.6171794,93.7617618
0.12653878249686
0
Ceiling fitting server room-fan,Downlighter

Progress Update : 26/06/2022
Conpleted
1
AE2ED3
24.618311056730775,93.76162934303298
24.6171794,93.7617618
0.12653878249686
0
Fire Extinguisher

Progress Update : 26/06/2022
Conpleted
1
AE2ED3
24.618311056730775,93.76162934303298
24.6186696,93.7614443
0.044036093356948
0
Lift

Progress Update : 26/06/2022
Conpleted
1
AE2ED3
24.618311056730775,93.76162934303298
24.6171794,93.7617618
0.12653878249686
0
MCB DB

Progress Update : 26/06/2022
Conpleted
1
AE2ED3
24.618311056730775,93.76162934303298
24.6171794,93.7617618
0.12653878249686
0
Main Distribution Panel

Progress Update : 26/06/2022
Conpleted
1
AE2ED3
24.618311056730775,93.76162934303298
24.6171794,93.7617618
0.12653878249686
0
LED Downlighter

Progress Update : 26/06/2022
Conpleted
1
AE2ED3
24.618311056730775,93.76162934303298
24.6186696,93.7614443
0.044036093356948
0
AC outdoor unit

Progress Update : 26/06/2022
Conpleted
1
AE2ED3
24.618311056730775,93.76162934303298
24.6186696,93.7614443
0.044036093356948
0
DG set

Progress Update : 26/06/2022
Conpleted
1
AE2ED3
24.618311056730775,93.76162934303298
24.6186696,93.7614443
0.044036093356948
0
Main building