Progress
 
 
Project Details
DAR-2022-000804
SFM/KwakeithelGirlsHSchool/Keishamthong
Implementation of School Fagathansi Mission-2nd Phase at Kwakeithel Girls High School Keishamthong A/C, Imphal West District.
08/11/2021
Education (S)
Imphal-West
70.30
59.47
State Plan
Completed
Nik
24.788784,93.923697
Implementation of School Fagathansi Mission-2nd Phase at Kwakeithel Girls High School Keishamthong A/C, Imphal West District. (Sh (i) Const. of 2 (two) Additional Classrooms & (ii) Repairing/Renovation of Classrooms & School Building (Sh Providing of IEI)
Progress Update : 22/03/2024
Completed
Nik
so4.eew-mn
24.788784,93.923697
24.78886,93.9237163
0.0086720144637317
0
Repairing inside view

Progress Update : 22/03/2024
Completed
Nik
so4.eew-mn
24.788784,93.923697
24.7889498,93.9236127
0.020304305190368
0
Repairing verandah view

Progress Update : 22/03/2024
Completed
Nik
so4.eew-mn
24.788784,93.923697
24.7889655,93.923605
0.022215413636111
0
Repairing front view

Progress Update : 22/03/2024
Completed
Nik
so4.eew-mn
24.788784,93.923697
24.7889577,93.9236152
0.021004590622678
0
Repairing front view-IEI

Progress Update : 22/03/2024
Completed
Nik
so4.eew-mn
24.788784,93.923697
24.7889405,93.9236103
0.019478157398657
0
IEI-MCB

Progress Update : 22/03/2024
Completed
Nik
so4.eew-mn
24.788784,93.923697
24.7889219,93.9236429
0.01627639906029
0
Construction 2ACR- inside room

Progress Update : 22/03/2024
Completed
Nik
so4.eew-mn
24.788784,93.923697
24.7888485,93.9241811
0.049390717550808
0
Construction 2ACR- inside view-IEI

Progress Update : 22/03/2024
Completed
Nik
so4.eew-mn
24.788784,93.923697
24.7889738,93.9235989
0.023311632137021
0
Construction 2ACR- verandah view

Progress Update : 22/03/2024
Completed
Nik
so4.eew-mn
24.788784,93.923697
24.7889227,93.9237098
0.015476038492197
0
Construction 2ACR- Side view

Progress Update : 22/03/2024
Completed
Nik
so4.eew-mn
24.788784,93.923697
24.7889867,93.9235665
0.026105605695315
0
Construction 2ACR- Front view

Progress Update : 22/03/2024
Completed
Nik
so4.eew-mn
24.788784,93.923697
24.7889432,93.923669
0.017925827939561
0
Construction 2ACR- Front view-IEI

Progress Update : 16/12/2022
In progress
Nil
so4.eew-mn
24.788784,93.923697
24.7889373,93.9235303
0.023952285640306
0
Repairing-inside room view-07

Progress Update : 16/12/2022
In progress
Nil
so4.eew-mn
24.788784,93.923697
24.7889726,93.9237087
0.021003517991238
0
Repairing-verandah view-06

Progress Update : 16/12/2022
In progress
Nil
so4.eew-mn
24.788784,93.923697
24.7889499,93.9235169
0.025899566920634
0
Repairing-Front view-05

Progress Update : 23/07/2022
In progress
Nil
so4.eew-mn
24.788784,93.923697
24.7890257,93.9236242
0.027861158635419
0
Repairing- verandah view

Progress Update : 23/07/2022
In progress
Nil
so4.eew-mn
24.788784,93.923697
24.7875858,93.9220318
0.21448776652485
0
Repairing- inside room view

Progress Update : 23/07/2022
In progress
Nil
so4.eew-mn
24.788784,93.923697
24.7893642,93.923291
0.076429438040822
0
Repairing- inside room view

Progress Update : 23/07/2022
In progress
Nil
so4.eew-mn
24.788784,93.923697
24.7888968,93.9236157
0.014988837880215
0
Repairing- Front view