Progress
 
 
Project Details
DAR-2022-000707
WRD-FCW-280
Improvement of Embankment along RBB of Thoubal River from RD 16.180 km to 16.300 km
02/05/2022
Water Resources Department (WRD)
Thoubal
16.00
0.00
State Plan
Completed
Last
24.652813177608632,93.9842519447746
Progress Update : 12/06/2022
Completed
Last
FCD-3
24.652813177608632,93.9842519447746
24.6527601,93.9844521
0.021070345588341
0
Improvement of embankment along RBB of Thoubal river from RD.16.180 km to 16.300km.