Progress
 
 
Project Details
DAR-2022-000667
Rejuvinition of Hiyanglam WSS/JJM/KAKCHING
Rejuvinition of Hiyanglam WSS
15/07/2020
PHED
Kakching
515.03
434.40
CSS / CPS
24.80748517734833,93.94173431396518
1.Energisation of pumpsets 2.Procurement of electric pump set(10HP and 15HP) 3.Improvement of step type intake 4.Improvement of Settling Tank 5.Improvement of SSF 6.Improvement Service Reservoir 7.Construction of internal pipe fittings 8.P/L of Filter Media 9.Laying and fixing of distribution pipeline 10.Cost of pipes & pipe specials 11.Energisation 12.Providing and fitting of FHTC 13.Procurement of electric pump set