Progress
 
 
Project Details
DAR-2022-000657
Extension of pipeline of Waikhong New WSS/JJM
Extension of pipeline of Waikhong New WSS
15/07/2020
PHED
Kakching
269.96
237.70
CSS / CPS
24.80748517734833,93.94173431396518
1.P/L of Filter Media 2.C/o of Boulder sausage and collection Chamber 3.Construction of internal pipe fittings 4.Energisation of the Scheme 5.L/F of distribution pipeline 6.Transportation of GI 7.Cost of G.I. pipes 80mm 8.Improvement of Settling Tank 9.Improvement of SSF 10.Improvement Service Reservoir-I 11.P/L of Filter Media 12.Laying and fixing of distribution and raw water pipeline 13.Repairing of dug well 14.Construction of Collection Chamber 15.Construction of Angle iron fencing 16.Providing and fitting of FHTC 17.Procurement of electric pump set