Progress
 
 
Project Details
DAR-2022-000623
Augmentation of Pallel WSS/JJM/KAKCHING
Augmentation of Pallel WSS
15/07/2020
PHED
Kakching
313.70
250.01
CSS / CPS
Ongoing
1
24.80748517734833,93.94173431396518
1.Construction of step type intake 2.Improvement of Settling Tank 3.Improvement of SSF 4.Improvement Service Reservoir 5.Construction of Service Reservoir 6.P/L of Filter Media 7.Laying and fixing of distribution pipeline 8.Cost of pipes & pipe specials 9.Construction of internal pipe fittings 10.Construction of Angle iron fencing with gate 11.Procurement of electric pump 12.Construction of Slow Sand Filter 13.P/L of Filter Media 14.Laying and fixing of distribution pipeline 15.Cost of pipes & pipe specials 16.Construction of Chawkidar Qtrs cum Godown 17.Providing and fitting of FHTC 18.Procurement of electric pump set
Progress Update : 02/03/2023
Ongoing
1
bikashpan
24.80748517734833,93.94173431396518
24.4510198,94.0247258
40.513141273148
0
Step type intake pumphouse

Progress Update : 02/03/2023
Ongoing
1
bikashpan
24.80748517734833,93.94173431396518
24.450604,94.0263349
40.592324644566
0
Laying of raw water main and distribution pipeline