Progress
 
 
Project Details
DAR-2022-000428
SP/22-DI/PerimeterWallNTomchouHr.Sec.S/IW
Construction of Perimeter Wall at N. Tomchou hr. Sec. School, Imphal West District, Manipur.
29/10/2021
Education (S)
Imphal-West
10.00
0.00
State Plan
Completed
Nil
24.624078257437876,93.89136635522534
Construction of Perimeter Wall at N. Tomchou hr. Sec. School, Imphal West District, Manipur.
Progress Update : 14/05/2022
Completed
Nil
so5.eew
24.624078257437876,93.89136635522534
24.624202,93.8908973
0.049367357111978
0
Outer wall

Progress Update : 14/05/2022
Completed
Nil
so5.eew
24.624078257437876,93.89136635522534
24.6242016,93.8908954
0.049539381394426
0
Outer wall

Progress Update : 14/05/2022
Completed
Nil
so5.eew
24.624078257437876,93.89136635522534
24.6242012,93.8908933
0.049731200814717
0
Inside wall

Progress Update : 14/05/2022
Completed
Nil
so5.eew
24.624078257437876,93.89136635522534
24.6242016,93.8908931
0.049762902645791
0
Inside wall