Progress
 
 
Project Details
DAR-2022-000376
Chandel Khullen UPS SMDC 2020-21
Upper Primary School Chandel Khullen UPS
31/08/2021
Edu (S) - SSA & RMSA
Chandel
27.23
9.39
CSS / CPS
Roofing level
Nil
24.328586838136722,93.98734545727237
Construction of 3 classroom & IEI with CGI roofing sanction under SSA in the year 2020-21 . SH: Construction of 3 classrooms with IEI
Progress Update : 05/05/2022
Roofing level
Nil
ssacdltpl
24.328586838136722,93.98734545727237
24.328679,93.9875119
0.019732808678897
0
Construction of 3 classrooms

Progress Update : 05/05/2022
Roofing level
Nil
ssacdltpl
24.328586838136722,93.98734545727237
24.3292111,93.991829
0.45952471099099
0
Construction of 3 classrooms

Progress Update : 05/05/2022
Roofing level
Nil
ssacdltpl
24.328586838136722,93.98734545727237
24.3285416,93.987264
0.0096647689540585
0
Construction of 3 classrooms

Progress Update : 05/05/2022
Roofing level
Nil
ssacdltpl
24.328586838136722,93.98734545727237
24.32702,93.9871617
0.1752080304368
0
Construction of 3 classrooms

Progress Update : 05/05/2022
Roofing level
Nil
ssacdltpl
24.328586838136722,93.98734545727237
24.3292111,93.991829
0.45952471099099
0
Construction of 3 classrooms

Progress Update : 05/05/2022
Roofing level
Nil
ssacdltpl
24.328586838136722,93.98734545727237
24.32702,93.9871617
0.1752080304368
0
Construction of 3 classrooms

Progress Update : 05/05/2022
Roofing level
Nil
ssacdltpl
24.328586838136722,93.98734545727237
24.3299526,93.991829
0.47896223647129
0
Construction of upper primary school ( 3 classrooms) at chandel khullen ups

Progress Update : 05/05/2022
Roofing level
Nil
ssacdltpl
24.328586838136722,93.98734545727237
24.3299526,93.991829
0.47896223647129
0
Construction of upper primary school ( 3 classrooms) at chandel khullen ups

Progress Update : 05/05/2022
Roofing level
Nil
ssacdltpl
24.328586838136722,93.98734545727237
24.32860302,93.9874167
0.0074385966227933
0
Construction of upper primary school ( 3 classrooms) at chandel khullen ups