DAR-2022-000352
SFM/22-DI/BishnulalHSSaitu/Kangpokpi
Implementation of School Fagathansi Mission-2nd Phase at Bishnulal High School, Saitu A/C, Kangpokpi District, Manipur
2021-11-08
Education (S)
Kangpokpi
70.01
58.64
State Plan
Completed
Nil
24.99485713569594,93.90000237354748
Implementation of School Fagathansi Mission-2nd Phase at Bishnulal High School, Saitu A/C, Kangpokpi District, Manipur (Sh (i) Construction of Girls Toilet i/c Septic Tank & (ii) Repairing/Renovation of Classrooms and Head Master) (Part-B) (Providing of IEI)
Progress Update : 2024-09-03
Completed
Nil
so4.eew-mn
24.99485713569594,93.90000237354748
24.9944706,93.8979542
0.21083454875849
Approved
0
IEI of classrooms have been completed

Progress Update : 2024-09-03
completed
Nil
so4.eew-mn
24.99485713569594,93.90000237354748
24.9944889,93.8978663
0.219124926801
Approved
2026-01-27 06:13:40
ee1.eew
0
Room IEI

Progress Update : 2024-09-03
Completed
Nil
so4.eew-mn
24.99485713569594,93.90000237354748
24.9944989,93.8980414
0.20159402858538
Approved
2026-01-27 06:13:03
ee1.eew
0
Room IEI

Progress Update : 2024-03-19
Completed
Nil
so4.eew-mn
24.99485713569594,93.90000237354748
24.9946161,93.8981755
0.18604599556531
Approved
2026-01-27 06:12:28
ee1.eew
0
Front View IEI

Progress Update : 2024-03-19
Completed
Nil
so4.eew-mn
24.99485713569594,93.90000237354748
24.9946819,93.8980177
0.20095481380367
Approved
0
Repairing of rooms and girls toilet has been completed

Progress Update : 2024-03-19
Completed
Nil
so4.eew-mn
24.99485713569594,93.90000237354748
24.9946737,93.8980032
0.20249904193985
Approved
2024-04-26 06:51:05
ee1.eew
0
Repairing of rooms and girls toilet has been completed

Progress Update : 2024-03-19
Completed
Nil
so4.eew-mn
24.99485713569594,93.90000237354748
24.9946802,93.8980106
0.20168531365075
Approved
0
Repairing of rooms and girls toilet has been completed

Progress Update : 2024-03-19
Completed
Nil
so4.eew-mn
24.99485713569594,93.90000237354748
24.9946695,93.8979496
0.20792023251571
Approved
0
Repairing of rooms and girl s toilet has been completed

Progress Update : 2022-07-28
Inprogess
Nil
sur1.eew-mn
24.99485713569594,93.90000237354748
24.9946953,93.8982466
0.17785294536654
Approved
2024-09-09 09:04:27
ee1.eew
0
Front view

Progress Update : 2022-04-06
Inprogess
Nil
sur1.eew-mn
24.99485713569594,93.90000237354748
24.9936681,93.8994237
0.14449876090957
Approved
2022-04-06 09:13:59
ee1.eew
0
Room

Progress Update : 2022-04-05
In progress
Nil
sur1.eew-mn
24.99485713569594,93.90000237354748
24.9947619,93.9000604
0.01209612717869
Approved
0
Tubular

Progress Update : 2022-04-05
In progress
Nil
sur1.eew-mn
24.99485713569594,93.90000237354748
24.994919,93.8981169
0.19013528120036
Approved
2022-04-05 09:27:16
ee1.eew
0
Verandah

Progress Update : 2022-04-05
In progress
Nil
sur1.eew-mn
24.99485713569594,93.90000237354748
24.9947619,93.9000604
0.01209612717869
Approved
2022-04-05 09:26:50
ee1.eew
0
Front view

Foundation & Inauguration
-
-
-

-
-
-