Progress
 
 
Project Details
DAR-2022-000276
MSPDCL-DDUGJY-093
Supply and Installation of 1,20,000 Nos. of Single Phase Pre-paid energy meter (Complete set) with Pilfer proof box in Valley districts of Manipur
2020-12-19
POWER (MSPDCL)
Imphal
13758.86
0.00
Central and State Share
Meter
Phase-1
24.803503,93.935297
Supply and Installation of 1,20,000 Nos. of Single Phase Pre-paid energy meter (Complete set) with Pilfer proof box in Valley districts of Manipur on turn key basis M/S Shyama Power India Limited
Progress Update : 2022-03-23
Meter
Phase-1
syamapower
24.803503,93.935297
24.6064176,93.894012
22.307126783178
Approved
2022-03-24 08:28:37
mspdcladmin
0
Valley

Progress Update : 2022-03-23
Meter
Phase-1
syamapower
24.803503,93.935297
24.6053913,93.8927413
22.443472837125
Approved
2022-03-24 08:33:11
mspdcladmin
0
Valley

Progress Update : 2022-03-23
Meter
Phase-1
syamapower
24.803503,93.935297
24.6181935,93.892758
21.047732094995
Approved
2022-03-24 08:39:04
mspdcladmin
0
Valley

Progress Update : 2022-03-23
Meter
Phase-1
syamapower
24.803503,93.935297
24.6175114,93.8916898
21.144198412664
Approved
2022-03-24 08:39:39
mspdcladmin
0
Valley

Progress Update : 2022-03-23
Meter
Phase-1
syamapower
24.803503,93.935297
24.6175085,93.8916889
21.144532736282
Approved
2022-03-24 08:40:07
mspdcladmin
0
Valley

Progress Update : 2022-03-23
Meter
Phase-1
syamapower
24.803503,93.935297
24.6154747,93.887646
21.453680070988
Approved
2022-03-24 08:54:05
mspdcladmin
0
Valley

Progress Update : 2022-03-23
Meter
Phase-1
syamapower
24.803503,93.935297
24.6159638,93.8879941
21.392804372513
Approved
2022-03-24 08:54:36
mspdcladmin
0
Valley

Progress Update : 2022-03-23
Meter
Phase-1
syamapower
24.803503,93.935297
24.8130173,93.927989
1.2896385153119
Approved
2022-03-24 08:55:02
mspdcladmin
0
Valley

Progress Update : 2022-03-23
Meter
Phase-1
syamapower
24.803503,93.935297
24.819721,93.93181
1.8372930563445
Approved
2022-03-24 08:55:51
mspdcladmin
0
Valley

Progress Update : 2022-03-23
Meter
Phase-1
syamapower
24.803503,93.935297
24.8180184,93.9333283
1.6261457846261
Approved
2022-03-24 08:56:24
mspdcladmin
0
Valley

Progress Update : 2022-03-23
Meter
Phase-1
syamapower
24.803503,93.935297
24.8192145,93.9331956
1.7597819405877
Approved
2022-03-24 08:56:51
mspdcladmin
0
Valley

Foundation & Inauguration
-
-
-

-
-
-