Progress
 
 
Project Details
DAR-2022-000246
150 SR/Approach road , JNIMS
Construction of 150 capacity Resident Doctor's (Boys) Hostel at J.N. Institue of Medical Sciences, Porompat Imphal (Sh:- Construction of Approach road
11/03/2016
PWD
Imphal-East
94.97
0.00
MH:8443 - CD
Completed
Final phase
24.812821859398184,93.96060405924682
Construction of approach road and parking area i/c road side drains
Progress Update : 08/03/2022
Completed
Final phase
ranjan
24.812821859398184,93.96060405924682
24.8136014,93.9605413
0.086907878379016
0
Completed

Progress Update : 08/03/2022
Completed
Final phase
ranjan
24.812821859398184,93.96060405924682
24.8134027,93.9606181
0.064598949669511
0
Completed

Progress Update : 08/03/2022
Completed
Final phase
ranjan
24.812821859398184,93.96060405924682
24.8134027,93.9606181
0.064598949669511
0
Completed

Progress Update : 08/03/2022
Completed
Final phase
ranjan
24.812821859398184,93.96060405924682
24.8139265,93.9606465
0.12289922442026
0
Completed