Progress
 
 
Project Details
DAR-2022-000130
KAK/NDB/RWS/P-X/10
Kharungpat Water Supply
14/10/2021
PHED
Kakching
100.00
0.00
EAP
24.547713977709137,93.96076726913466
1 Construction of Intake Weir 2 C/O aerator 2 Construction of Settling Tank 3 Construction of Slow Sand Filter 4 Construction of Service Reservoir 5 P/L of Filter Media 6 P/L of distribution and raw water pipeline 7 Cost of pipes & pipe specials 8 C/o of internal pipefittings 9 C/O angle iron fencing 10 C/o Pump House 11 Energisation 12 Procurement of pumpsets 13 C/o Land development and approach road