DAR-2022-000122
KAK/NDB/RWS/P-X/2
Augmentation of Waikhong (New) WSS
14/10/2021
PHED
Kakching
197.00
0.00
EAP
24.414196932771688,93.93043684959426
1.Construction of Intake Weir
2.Construction of Settling Tank
3.Improvement of Service Reservoir
4.Improvement of Slow Sand Filter
5.P/L of Filter Media
6.P/L of distribution and raw water pipeline
7.Cost of pipes & pipe specials
8.C/o Internal pipe fittings
9.C/o angle iron fencing
10.C/o Pump House cum godown
11.Energisation
12.Procurement of pumpsets