Progress
 
 
Project Details
DAR-2022-000122
KAK/NDB/RWS/P-X/2
Augmentation of Waikhong (New) WSS
14/10/2021
PHED
Kakching
197.00
0.00
EAP
24.414196932771688,93.93043684959426
1.Construction of Intake Weir 2.Construction of Settling Tank 3.Improvement of Service Reservoir 4.Improvement of Slow Sand Filter 5.P/L of Filter Media 6.P/L of distribution and raw water pipeline 7.Cost of pipes & pipe specials 8.C/o Internal pipe fittings 9.C/o angle iron fencing 10.C/o Pump House cum godown 11.Energisation 12.Procurement of pumpsets