Progress
 
 
Project Details
DAR-2022-000116
EE/ED-II/SDO Japhou/105
Maint. of IEI in the SDO office at Japhou
09/12/2021
PWD
Chandel
6.00
0.00
2059
Completed
1
24.33316321601568,94.0020589891657
IEI & it's accessories
Progress Update : 08/02/2022
Completed
1
8014345027
24.33316321601568,94.0020589891657
24.331853333333,94.001195
0.16992518565507
0
Mandol room switch socket

Progress Update : 08/02/2022
Completed
1
8014345027
24.33316321601568,94.0020589891657
24.331853333333,94.001195
0.16992518565507
0
Mandol room ceiling fitting

Progress Update : 08/02/2022
Completed
1
8014345027
24.33316321601568,94.0020589891657
24.331853333333,94.001195
0.16992518565507
0
Room no 6 ceiling fitting

Progress Update : 08/02/2022
Completed
1
8014345027
24.33316321601568,94.0020589891657
24.331853333333,94.001195
0.16992518565507
0
Room no 6 switch socket

Progress Update : 08/02/2022
Completed
1
8014345027
24.33316321601568,94.0020589891657
24.331853333333,94.001195
0.16992518565507
0
Verandah

Progress Update : 08/02/2022
Completed
1
8014345027
24.33316321601568,94.0020589891657
24.331466666667,94.001165
0.20925558347052
0
General section ceiling fitting

Progress Update : 08/02/2022
Completed
1
8014345027
24.33316321601568,94.0020589891657
24.331466666667,94.001165
0.20925558347052
0
General section room switch docket

Progress Update : 08/02/2022
Completed
1
8014345027
24.33316321601568,94.0020589891657
24.331598333333,94.001218333333
0.19372482806437
0
SDO room ceiling fitting

Progress Update : 08/02/2022
Completed
1
8014345027
24.33316321601568,94.0020589891657
24.331598333333,94.001218333333
0.19372482806437
0
SDO room switch socket

Progress Update : 08/02/2022
Completed
1
8014345027
24.33316321601568,94.0020589891657
24.331863333333,94.001141666667
0.17183440355223
0
Computer room switch socket

Progress Update : 08/02/2022
Completed
1
8014345027
24.33316321601568,94.0020589891657
24.341746666667,94.002878333333
0.95799313778982
0
SDO Office