Progress
 
 
Project Details
DAR-2021-002052
Chingangbam Leikai Upper Primary School SMDC
Upper Primary School (UPS)
2018-03-31
Edu (S) - SSA & RMSA
Imphal-East
29.79
11.45
CSS / CPS
Completed
Completed
24.8194548,93.96352410000001
Construction of 3 (three) Classroom with I.E.I at Chingangbam Leikai U.P.S has been Completed.
Progress Update : 2021-12-16
Completed
Completed
ssaiejbm
24.8194548,93.96352410000001
24.8157406,93.9651637
0.44489675543911
Approved
2022-03-24 09:24:47
ssarmsaadmin
0
Construction of 3 (three) Classroom with I.E.I has been completed.

Progress Update : 2021-12-16
Completed
Completed
ssaiejbm
24.8194548,93.96352410000001
24.815631,93.9652822
0.46070373550789
Approved
2022-03-24 09:25:00
ssarmsaadmin
0
Construction of 3 (three) Classroom with I.E.I has been completed.

Progress Update : 2021-12-16
Completed
Completed
ssaiejbm
24.8194548,93.96352410000001
24.8156361,93.9652805
0.46011432669449
Approved
2022-03-24 09:25:14
ssarmsaadmin
0
Construction of 3 (three) Classroom with I.E.I has been completed.

Foundation & Inauguration
-
-
-

-
-
-