Progress
 
 
Project Details
DAR-2021-002014
DivnII Lambal Lairam(Item 1)
Development of Irrigation in Imphal West(7 Items of Works)
08/11/2021
CADA
Imphal-West
3.56
0.00
State Plan
Completed
First & Final
24.8461947,93.8428522
Conts. of Lined Field Channels FC-1 to 3 from Lambal lairam Loukhong to Lairam Loukol Taba at Lambal, Imphal West District
Progress Update : 12/12/2021
Completed
First & Final
EEDIVN2
24.8461947,93.8428522
24.8461947,93.8428522
0
0
Conts. of Lined Field Channels FC-1 to 3 from Lambal Lairam Loukhong to Lairam Loukol Taba at Lambal, Imphal West District