Progress
 
 
Project Details
DAR-2021-001982
LATINGKHAL PRIMARY SCHOOL SMDC 2018-19
Boys Toilet LATINGKHAL P/S
2019-04-04
Edu (S) - SSA & RMSA
Jiribam
4.46
1.52
CSS / CPS
Completed
Nil
24.727466239104785,93.10025379695892
Construction Of Boys Toilet approved in the year 2018-19 at LATINGKHAL P/S . Construction Of Boys Toilet with IEI.
Progress Update : 2021-12-14
Completed
Nil
ssaiejbm
24.727466239104785,93.10025379695892
24.7311316,93.1025579
0.46930298769783
Approved
2022-07-25 05:49:19
ssarmsaadmin
0
Construction of Boys toilet

Progress Update : 2021-12-14
Completed
Nil
ssaiejbm
24.727466239104785,93.10025379695892
24.72747579,93.10031234
0.0060069477925679
Approved
2022-07-25 05:49:30
ssarmsaadmin
0
Construction of Boys toilet

Progress Update : 2021-12-14
Completed
Nil
ssaiejbm
24.727466239104785,93.10025379695892
24.7275004,93.10031635
0.0073716631041039
Approved
2022-07-25 05:49:43
ssarmsaadmin
0
Construction of Boys toilet

Progress Update : 2021-12-14
Completed
Nil
ssaiejbm
24.727466239104785,93.10025379695892
24.7263389,93.1013047
0.16424678960428
Approved
2022-07-25 05:49:59
ssarmsaadmin
0
Construction of Boys toilet

Progress Update : 2021-12-14
Completed
Nil
ssaiejbm
24.727466239104785,93.10025379695892
24.72776702,93.10023732
0.033485124771612
Approved
2022-07-25 05:50:18
ssarmsaadmin
0
Construction of Boys toilet

Progress Update : 2021-12-14
Completed
Nil
ssaiejbm
24.727466239104785,93.10025379695892
24.7315022,93.1025579
0.50550057812254
Approved
2022-07-25 05:50:34
ssarmsaadmin
0
Construction of Boys toilet

Progress Update : 2021-12-14
Completed
Nil
ssaiejbm
24.727466239104785,93.10025379695892
24.7263131,93.1025579
0.26568789833964
Approved
2022-07-25 05:51:01
ssarmsaadmin
0
Construction of Boys toilet

Progress Update : 2021-12-14
Completed
Nil
ssaiejbm
24.727466239104785,93.10025379695892
24.7263131,93.1025579
0.26568789833964
Approved
2022-07-25 05:51:10
ssarmsaadmin
0
Construction of Boys toilet

Foundation & Inauguration
-
-
-

-
-
-