Progress
 
 
Project Details
DAR-2021-001936
Ramlalong Primary School SMDC 2014-15
Additional Class Room
2015-10-01
Edu (S) - SSA & RMSA
Tamenglong
8.67
4.96
CSS / CPS
Completed
Complete
24.930924,93.445518
Construction of 1 Additional Class Room taken up in the year 2014-15 at Ramlalong Primary School. Construction of 1 Additional Class Room with IEI
Progress Update : 2021-11-27
Completed
Complete
ssatmlnoney
24.930924,93.445518
24.9310438,93.44464778
0.088748302462011
Approved
2021-12-04 08:15:04
ssarmsaadmin
0
1 Additional Class Room at Ramlalong Primary School

Progress Update : 2021-11-27
Completed
Complete
ssatmlnoney
24.930924,93.445518
24.9309155,93.44541225
0.01070446595586
Approved
2021-12-04 08:15:13
ssarmsaadmin
0
1 Additional Class Room at Ramlalong Primary School

Progress Update : 2021-11-27
Completed
Complete
ssatmlnoney
24.930924,93.445518
24.93092274,93.44540763
0.011129590752148
Approved
2021-12-04 08:15:21
ssarmsaadmin
0
1 Additional Class Room at Ramlalong Primary School

Progress Update : 2021-11-27
Completed
Complete
ssatmlnoney
24.930924,93.445518
24.93089862,93.4454227
0.010014179726952
Approved
2021-12-04 08:15:32
ssarmsaadmin
0
1 Additional Class Room at Ramlalong Primary School

Foundation & Inauguration
-
-
-

-
-
-