Progress
 
 
Project Details
DAR-2021-001935
MSPDCL-STATEPLAN-082
Supply of Distribution Transformers(250KVA,100KVA,63KVA & 25KVA) as per IS:1180(Part-I):2014 with Energy Efficiency Level-2(4 star rating)
21/06/2021
POWER (MSPDCL)
ALL MANIPUR
202.77
0.00
State Plan
Ongoing
NA
24.79021,93.87118
Supply of Distribution Transformers(250KVA,100KVA,63KVA & 25KVA) as per IS:1180(Part-I):2014 with Energy Efficiency Level-2(4 star rating)
Progress Update : 25/11/2021
Ongoing
NA
Rajesh
24.79021,93.87118
24.7905904,93.8712857
0.043621367941077
0
Supply of distribution transformer.

Progress Update : 25/11/2021
Ongoing
NA
Rajesh
24.79021,93.87118
24.790591,93.8712905
0.043807009386379
0
Supply of distribution transformer.

Progress Update : 25/11/2021
Ongoing
NA
Rajesh
24.79021,93.87118
24.790591,93.8712905
0.043807009386379
0
Supply of distribution transformer.

Progress Update : 25/11/2021
Ongoing
NA
Rajesh
24.79021,93.87118
24.7905732,93.8712875
0.041816528851339
0
Supply of distribution transformer.

Progress Update : 25/11/2021
Ongoing
NA
Rajesh
24.79021,93.87118
24.7905676,93.871306
0.041746105822013
0
Supply of distribution transformer.