Progress
 
 
Project Details
DAR-2021-001923
Uchiwa Nastao Upper Primary School SMDC
Major Repairing Uchiwa Nastao Upper Primary School
2019-04-04
Edu (S) - SSA & RMSA
Thoubal
4.03
1.39
CSS / CPS
Completion
Completed
24.592344232462725,93.91147899627693
Major Repairing at Uchiwa Nastao Upper Primary School approved in 2017-18 Thoubal District
Progress Update : 2021-11-22
Completion
Completed
ssatblkak
24.592344232462725,93.91147899627693
24.5937536,93.9108857
0.16779505439852
Approved
2021-12-29 10:33:35
ssarmsaadmin
0
Major Repairing at Uchiwa Nastao Upper Primary School

Progress Update : 2021-11-22
Completion
Completed
ssatblkak
24.592344232462725,93.91147899627693
24.5896774,93.9108857
0.30253046154198
Approved
2021-12-29 10:33:19
ssarmsaadmin
0
Major Repairing at Uchiwa Nastao Upper Primary School

Progress Update : 2021-11-22
Completion
Completed
ssatblkak
24.592344232462725,93.91147899627693
24.5896774,93.9108857
0.30253046154198
Approved
2021-12-29 10:33:07
ssarmsaadmin
0
Major Repairing at Uchiwa Nastao Upper Primary School

Foundation & Inauguration
-
-
-

-
-
-