Progress
 
 
Project Details
DAR-2021-001884
H&SC/SCA/VF&CCPH/2020-21
“Establishment of Coldchain Infrastructures, Vacuum Freeze Dehydration (Food Processing) and Integrated Packhouse”
06/11/2020
Horticulture & Soil Conservation
Imphal-East
2259.00
329.49
Scheme for Special Assistance to States for Capit
Ongoing
Ongoing
24.884697, 93.907002
“Establishment of Coldchain Infrastructures, Vacuum Freeze Dehydration (Food Processing) and Integrated Packhouse” under Scheme for Special Assistance to States for Capital Expenditure at Imphal East and Imphal West Districts of the state. Creation of Post Harvest infrastructures and processing units for reducing post harvest ;ossed of the highly perishable horticulture products of the state.
Progress Update : 16/11/2021
Ongoing
Ongoing
hscSCAdo@VF&CCPH
24.884697, 93.907002
24.8848734,93.9073119
0.036902543413669
329.49
Name of Project: Establishment of Vacuum Freeze Dehydration & Coldchain Infrastructure. Component: Vacuum Freeze Dehydration at Nilakuthi, Imphal East under the Project. About 60% of the Civil Construction work completed.

Progress Update : 16/11/2021
Ongoing
Ongoing
hscSCAdo@VF&CCPH
24.884697, 93.907002
24.8851732,93.9062204
0.094967414186803
329.49
Name of Project: Establishment of Vacuum Freeze Dehydration & Coldchain Infrastructure. Component: Vacuum Freeze Dehydration at Nilakuthi, Imphal East under the Project. About 60% of the Civil Construction work completed.

Progress Update : 16/11/2021
Ongoing
Ongoing
hscSCAdo@VF&CCPH
24.884697, 93.907002
24.8839787,93.9035624
0.35601514854724
329.49
Name of Project: Establishment of Vacuum Freeze Dehydration & Coldchain Infrastructure. Component: Vacuum Freeze Dehydration at Nilakuthi, Imphal East under the Project. About 60% of the Civil Construction work completed.

Progress Update : 16/11/2021
Ongoing
Ongoing
hscSCAdo@VF&CCPH
24.884697, 93.907002
24.8845416,93.9067619
0.029750145946647
329.49
Establishment of Vaccum Freeze Dehydration & Coldchain infrastructure

Progress Update : 16/11/2021
Ongoing
Ongoing
hscSCAdo@VF&CCPH
24.884697, 93.907002
24.8845156,93.9068354
0.026252766997005
329.49
Establishment of Vaccum Freeze Dehydration & Coldchain infrastructure

Progress Update : 16/11/2021
Ongoing
Ongoing
hscSCAdo@VF&CCPH
24.884697, 93.907002
24.8845213,93.9069599
0.01999233071552
329.49
Name of Project: Establishment of Vacuum Freeze Dehydration & Coldchain Infrastructure. Component: Vacuum Freeze Dehydration at Nilakuthi, Imphal East under the Project. About 60% of the Civil Construction work completed.

Progress Update : 16/11/2021
Ongoing
Ongoing
hscSCAdo@VF&CCPH
24.884697, 93.907002
24.8846431,93.907026
0.00646296333701
329.49
Name of Project: Establishment of Vacuum Freeze Dehydration & Coldchain Infrastructure. Component: Vacuum Freeze Dehydration at Nilakuthi, Imphal East under the Project. About 60% of the Civil Construction work completed.