Progress
 
 
Project Details
DAR-2021-001852
RENGKAI HR. EC SCHOOL
CONST. OF TWO ACR under ENG. WING
31/10/2019
Edu (S) - SSA & RMSA
Churachandpur
27.38
10.95
CSS / CPS
24.342666547855092,93.7045263252312
The construction of two class room is completed upto roofing level, plaster work is in progress. one toilet and one library work is not started till now. eng. wing have submitted utilization certificate for only 2 ACR