Progress
 
 
Project Details
DAR-2021-001589
WRD-FCW-167
Channelisation of Muklang Stream at Umathel
2021-07-20
Water Resources Department (WRD)
Kakching
19.00
11.40
State Plan
Completed
Final phase
24.38078611111,93.886194444
Progress Update : 2021-10-12
Completed
Final phase
FCD-3
24.38078611111,93.886194444
24.383613,93.8763796
1.0424908165719
Approved
2021-10-21 12:07:26
approverifcd
0
Channelisation of Muklang Stream at Umathel

Foundation & Inauguration
-
-
-

-
-
-