Progress
 
 
Project Details
DAR-2017-000166
WRD-SBP-01
Sekmai Barrage Project(Medium-ERM), Manipur
12/08/2013
Water Resources Department (WRD)
Kakching
1020.00
0.00
State Plan
Completed
Final
24.51258112027559,93.96285402774834
The project is to be taken up for renovation of canal systems and structures on the canal system of the Sekmai Barrage Project for improvement of irrigation system.
Progress Update : 24/05/2018
Completed
Final
IMD-2
24.51258112027559,93.96285402774834
24.4950605,93.9564476
2.0531097963476
0
Improvement of the left side of the 170 cusecs main canal bund from RD 1500 m to RD 2350 m

Progress Update : 23/05/2018
Completed
Final
IMD-2
24.51258112027559,93.96285402774834
24.4801013,93.9547645
3.7030110833504
0
Repairing and replacement of crossing bridge with RCC Pipe Culvert on 170 cusecs left main canal of Sekmai Barrage at RD 3700 m

Progress Update : 23/05/2018
Completed
Final
IMD-2
24.51258112027559,93.96285402774834
24.4396451,93.9313167
8.7151184639194
0
Repairing and replacement of crossing bridge with RCC Pipe Culvert on 170 cases left side main canal of Sekmai Barrage at RD 2010 m

Progress Update : 13/04/2018
Completed
Final
IMD-2
24.51258112027559,93.96285402774834
24.5096484,93.9529349
1.0551622326451
0
Removal of deposited earth at U/S of Sekmai Barrage along the R/B/B from RD 0 m to 150 m

Progress Update : 13/04/2018
Completed
Final
IMD-2
24.51258112027559,93.96285402774834
24.5096484,93.9529349
1.0551622326451
0
Removal of deposited earth at U/S of Sekmai Barrage along R/B/B from RD 150 m to 230 m

Progress Update : 22/02/2018
Completed
Final Phase
IMD-2
24.51258112027559,93.96285402774834
24.5025428,93.9411449
2.4636956519747
0
Improvement of US Irum river/maril from 0.00m to 1871.00m at Sekmai Barrage.

Progress Update : 22/02/2018
Completed
Final Phase
IMD-2
24.51258112027559,93.96285402774834
24.500532,93.9755665
1.857174393021
0
Clearance and removal of siltation of LS 170cusec main canal from RD 3150.00 m to 3880.00 m.

Progress Update : 22/02/2018
Completed
Final Phase
IMD-2
24.51258112027559,93.96285402774834
24.4982665,93.9771606
2.1513765522844
0
Clearance and removal of siltation of LS 170cusec main canal from RD 2350.00 m to 3150.00 m.

Progress Update : 22/02/2018
Completed
Final Phase
IMD-2
24.51258112027559,93.96285402774834
24.5025759,93.9398705
2.5777094577175
0
Clearance and removal of siltation of LS 170cusec main canal from RD 1890.00 m to 2350.00 m.

Progress Update : 22/02/2018
Completed
Final Phase
IMD-2
24.51258112027559,93.96285402774834
24.5025428,93.9411449
2.4636956519747
0
Clearance and removal of siltation of LS 170cusec main canal from RD 1340.00 m to 1890.00 m.

Progress Update : 22/02/2018
Completed
Final Phase
IMD-2
24.51258112027559,93.96285402774834
24.5025428,93.9411449
2.4636956519747
0
Clearance and removal of siltation of Distributors No.3 from RD 0.00m to 3240.00 m of 170 cusec Main Canal at RD 930.00m

Progress Update : 22/02/2018
Completed
Final Phase
IMD-2
24.51258112027559,93.96285402774834
24.5025759,93.9398705
2.5777094577175
0
Clearance and removal of siltation of LS 170 cusec main canal from RD 0.00m to 1340.00 m

Progress Update : 22/02/2018
Completed
Final Phase
IMD-2
24.51258112027559,93.96285402774834
24.5120524,93.96477
0.20255444077366
0
Removal of Siltation from the RS 40 Cusecs main canal of Cut and Cover/ Conduit from RD 0.00m to 130.00 m.

Progress Update : 22/02/2018
Completed
Final Phase
IMD-2
24.51258112027559,93.96285402774834
24.5120524,93.96477
0.20255444077366
0
Clearance and removal of siltation from RD 130.00 m 220.00 m of RS 40 cusec Main Canal

Progress Update : 25/12/2017
Completed
Final
IMD-2
24.51258112027559,93.96285402774834
24.5103231,93.9554844
0.78671567913039
0
Repairing of 32 KVA Diesel Generator set

Progress Update : 25/12/2017
Completed
Final
IMD-2
24.51258112027559,93.96285402774834
24.5145837,93.963351
0.22827165536521
0
Clearance and removal of siltation from RD 220 m to 1410 m of R/S 40 cusecs main canal

Progress Update : 19/12/2017
Completed
Final
IMD-2
24.51258112027559,93.96285402774834
24.5107789,93.9605447
0.3077974607914
0
Fencing of CGI Sheet walling and repairing of Officers colony quarter at Keirak

Progress Update : 19/12/2017
Completed
Final
IMD-2
24.51258112027559,93.96285402774834
24.5113006,93.9607499
0.25609869106533
0
Dismantling of sub-division at Mantak hill & repairing of old Office quarter buildings of Sekmai Barrage inside the godown complex at Keirak

Progress Update : 19/12/2017
Completed
Final
IMD-2
24.51258112027559,93.96285402774834
24.4983418,93.9575213
1.6726685508017
0
Improvement of L/S main canal of 170 cusecs from RD 1500 m to 2000 m

Progress Update : 18/12/2017
Completed
Final
IMD-2
24.51258112027559,93.96285402774834
24.5085047,93.9678492
0.67884417842871
0
Construction of head regulator at Chumnang Canal