Progress
 
 
Project Details
DAR-2021-001565
RR/21-DI/FrontierHS/UKL
Repairing/Renovation of Existing Infrastructure at Frontier High School.Ukhrul
2020-03-20
Education (S)
Ukhrul
15.00
0.00
State Plan
Completed
Nil
25.430574802207442,94.57513414907376
Repairing/Renovation of Existing Infrastructure at Frontier High School.Ukhrul
Progress Update : 2022-10-29
Completed
Nil
sur1.eew-mn
25.430574802207442,94.57513414907376
25.4247453,94.5761455
0.65608783080579
Approved
2022-11-22 08:40:24
ee1.eew
0
Room

Progress Update : 2022-10-29
Completed
Nil
sur1.eew-mn
25.430574802207442,94.57513414907376
25.4247453,94.5761455
0.65608783080579
Approved
2022-11-22 08:38:55
ee1.eew
0
Front view

Progress Update : 2022-10-29
Completed
Nil
sur1.eew-mn
25.430574802207442,94.57513414907376
25.4305329,94.5751198
0.0048767053700042
Approved
2022-11-22 08:41:01
ee1.eew
0
Verandah

Foundation & Inauguration
-
-
-

-
-
-