DAR-2021-001558
EE/SHD/Impvt rd Haraothel rd to Kharam Vaiphe
Impvt. of road from Haraothel road to Kharam Vaiphei via L. Phaijang
18/01/2021
PWD
Kangpokpi
125.00
17
State Plan
In progress
2020-21
24.908,93.825
6m span RCC slab culvert (2nos), NP3 pipe culvert, Earth cutting and banking, Kutcha drain
Progress Update : 23/02/2023
In progress
2020-21
Sadarhills
24.908,93.825
24.9085835,93.8253009
0.071624780100824
17
Hill Cutting

Progress Update : 23/02/2023
In progress
2020-21
Sadarhills
24.908,93.825
24.9085835,93.8253009
0.071624780100824
17
Hill cutting

Progress Update : 23/02/2023
In progress
2020-21
Sadarhills
24.908,93.825
24.9085835,93.8253009
0.071624780100824
17
Hill cutting

Progress Update : 23/02/2023
In progress
2020-21
Sadarhills
24.908,93.825
24.9085835,93.8253009
0.071624780100824
17
NP-3 Pipe culvert - completed

Progress Update : 21/09/2021
On going
2020-21
Sadarhills
24.908,93.825
24.9008561,93.8552847
3.155821227378
0
Earth cutting, kutcha drain, banking, 6m span Rcc slab culvert, NP3 pipe culvert

Progress Update : 21/09/2021
On going
2020-21
Sadarhills
24.908,93.825
24.9207021,93.8580544
3.6201426427496
0
Earth cutting, kutcha drain, banking, 6m span Rcc slab culvert, NP3 pipe culvert

Progress Update : 21/09/2021
On going
2020-21
Sadarhills
24.908,93.825
24.9497647,93.8558028
5.5866981761575
0
Earth cutting, kutcha drain, banking, 6m span Rcc slab culvert, NP3 pipe culvert