Progress
 
 
Project Details
DAR-2021-001554
JBM/Nongshaba Gate/31
Constn. of Prestigious Nongshaba Gate at Jiribam District
2019-03-08
PWD
Jiribam
107.50
36.00
State Plan
Nearing Completion 90%
Phase I
24.807623563394397,93.11309653366011
Progress Update : 2021-11-25
Nearing Completion 90%
Phase I
Satya
24.807623563394397,93.11309653366011
24.8075968,93.1125787
0.052349284315444
Approved
36
RCC structures, Brick works, Steel Truss completed. RCC slab, Roofing, Painting etc yet to complete.

Foundation & Inauguration
-
-
-

-
-
-