Project Details
DAR-2021-001526
ND/Road/Tendongyan/12
Impvt. of Tendongyan approach road i/c 2 nos of slab culvert.
21/03/2020
PWD
Noney
50.00
11
State Plan
In progress
Phase-I
24.65917510561397,93.5440633324707
GSB, WBM, Culvert & Kutcha Drain.
Progress Update : 27/09/2022
In progress
Phase-I
eenoney
24.65917510561397,93.5440633324707
24.6595517,93.5458883
0.18910639955538
11
P/L of WBM completed

Progress Update : 27/09/2022
In progress
Phase-I
eenoney
24.65917510561397,93.5440633324707
24.6595817,93.5462883
0.22933225128722
11
P/L of WBM in progress & completed kutcha drain

Progress Update : 29/11/2021
77%
Phase I
eenoneyd
24.65917510561397,93.5440633324707
24.6594083,93.5456333
0.16074957284003
0
E/work, GSB & WBM - II & III

Progress Update : 31/10/2021
76% completed
I
eenoney
24.65917510561397,93.5440633324707
24.6595685,93.5456714
0.1682788517993
0
P/L of WBM-II- 75mm