Progress
 
 
Project Details
DAR-2021-001406
EE/HS/Impvt rd Hiyangthang Tarahei to Langtha
Impvt. of road Hiyangthang Tarahei Thongkhong to Langthabal Mantrikhong Makha on Nambul lambi-2km
07/03/2020
PWD
Imphal-West
85.00
61.5
State Plan
Completed
I
24.73296045798012,93.90886423389894
GSB, WBM Grade-III and PC
Progress Update : 28/09/2022
Completed
I
mfrahman
24.73296045798012,93.90886423389894
24.7309595,93.9061095
0.35622538762486
61.5
Roadworks

Progress Update : 28/09/2022
Completed
I
mfrahman
24.73296045798012,93.90886423389894
24.7305974,93.9057911
0.40664303956917
42
Roadworks

Progress Update : 27/08/2021
On going
1
mfrahman
24.73296045798012,93.90886423389894
24.73539951,93.90987504
0.2897727856812
0
Road works

Progress Update : 27/08/2021
On going
1
mfrahman
24.73296045798012,93.90886423389894
24.73157811,93.90820392
0.16754539758982
0
Road works

Progress Update : 27/08/2021
On going
1
mfrahman
24.73296045798012,93.90886423389894
24.73059,93.9079474
0.27936089836492
0
Road works