Progress
 
 
Project Details
DAR-2021-001109
SS/19D-I-ChingkhamMakhaUPM/TBL
Strengthening of School under Samagra Shiksha (Elementary) 2019-20 Thoubal District.
16/12/2019
Education (S)
Thoubal
43.89
17.55
Samagra Shiksha
Completed
Nill
24.674223631649276,93.93611461111448
Strengthening of School under Samagra Shiksha (Elementary) 2019-20 (Sh: Construction of 3 (Three) ACR at Chingkham Makha UPM, Thoubal
Progress Update : 16/02/2023
Completed
Nill
so3.eew-mn
24.674223631649276,93.93611461111448
24.6761034,93.9357288
0.21261463868873
0
Inside and IEI

Progress Update : 16/02/2023
Completed
Nill
so3.eew-mn
24.674223631649276,93.93611461111448
24.6753708,93.9354102
0.14606576015819
0
Inside and IEI

Progress Update : 16/02/2023
Completed
Nill
so3.eew-mn
24.674223631649276,93.93611461111448
24.6742562,93.9359613
0.015908192607367
0
Front

Progress Update : 25/09/2022
Inprogess
Nil
sur1.eew-mn
24.674223631649276,93.93611461111448
24.6750003,93.9354102
0.11190630046125
0
Room

Progress Update : 25/09/2022
Inprogess
Nil
sur1.eew-mn
24.674223631649276,93.93611461111448
24.6741468,93.9359607
0.017742906541794
0
Verandah

Progress Update : 25/09/2022
Inprogess
Nil
sur1.eew-mn
24.674223631649276,93.93611461111448
24.6742341,93.9359848
0.013166998413322
0
Front view

Progress Update : 15/04/2021
Inprogess
Nil
sur1.eew-mn
24.674223631649276,93.93611461111448
24.6743239,93.9361008
0.0112355643017
0
Side view

Progress Update : 15/04/2021
Inprogess
Nil
sur1.eew-mn
24.674223631649276,93.93611461111448
24.6741984,93.9361375
0.0036372223478664
0
Side view

Progress Update : 15/04/2021
Inprogess
Nil
sur1.eew-mn
24.674223631649276,93.93611461111448
24.6740932,93.936069
0.015217369457253
0
Side view

Progress Update : 15/04/2021
Inprogess
Nil
sur1.eew-mn
24.674223631649276,93.93611461111448
24.6742653,93.9358981
0.02236097337812
0
Front view