Progress
 
 
Project Details
DAR-2021-001079
Repair/NH102/320/2020-21
Repairs of NH102- Clearance of chocked side drain and culverts, providing chequred tiles , reconstruction of drain walls, cover slab km 320.320-321.20
2021-03-17
PWD
Imphal-West
14.20
0.00
Completed
Completed
24.80227541440859,93.94095077365651
Clearance of chocked side drain and culverts, providing chequred tiles , reconstruction of drain walls, cover slab
Progress Update : 2021-03-19
Completed
Completed
nh2som
24.80227541440859,93.94095077365651
24.8017775,93.9408607
0.056104302693474
Approved
2021-03-19 07:05:14
senhc
0
Clearance of chocked side drain and providing chequered tiles.

Progress Update : 2021-03-19
Completed
Completed
nh2som
24.80227541440859,93.94095077365651
24.8015517,93.9410188
0.080761897081857
Approved
2021-03-19 07:05:26
senhc
0
Clearance of chocked side drain and providing chequered tiles.

Progress Update : 2021-03-19
Completed
Completed
nh2som
24.80227541440859,93.94095077365651
24.8015049,93.9407539
0.087947468534601
Approved
2021-03-19 07:05:38
senhc
0
Clearance of chocked side drain and providing chequered tiles.

Foundation & Inauguration
-
-
-

-
-
-