Progress
 
 
Project Details
DAR-2021-001069
EE/ED-II/Mesh Hall-IIIT/71
Maint. of IEI & replacement of existing ordinary fitting by LED bubl, tube in the Mesh Hall, Boys Hostel No. 1&2 for IIIT at Mantripukhri.
24/12/2019
PWD
Imphal-East
15.00
0.00
2059
completed
I
24.842189427051792,93.9424209594728
Progress Update : 18/03/2021
completed
I
8014345027
24.842189427051792,93.9424209594728
24.3621,93.70271
58.624186468587
0
MCB DB

Progress Update : 18/03/2021
completed
I
8014345027
24.842189427051792,93.9424209594728
24.3621,93.70271
58.624186468587
0
Cook room

Progress Update : 18/03/2021
completed
I
8014345027
24.842189427051792,93.9424209594728
24.3621,93.70271
58.624186468587
0
corridor lighting

Progress Update : 18/03/2021
completed
I
8014345027
24.842189427051792,93.9424209594728
24.3621,93.70271
58.624186468587
0
kitchen room switch & socket

Progress Update : 18/03/2021
completed
I
8014345027
24.842189427051792,93.9424209594728
24.3621,93.70271
58.624186468587
0
switch & socket

Progress Update : 18/03/2021
completed
I
8014345027
24.842189427051792,93.9424209594728
24.3621,93.70271
58.624186468587
0
Mesh hall ceiling fittings