Progress
 
 
Project Details
DAR-2021-001059
MO/NH-150/km 462.15/2020-21
M/O- Painting of central median, footpath, wall of Kekrupat from km 462.15 to km 465.200
2021-03-16
PWD
Imphal-West
8.00
0.00
MoRTH
Completed
1
24.814117127991555,93.93882143497481
Painting of central median, footpath, wall of Kekrupat
Progress Update : 2021-03-17
Completed
1
nh3pwdmanipur
24.814117127991555,93.93882143497481
24.814306,93.9388567
0.02130005291783
Approved
2021-03-18 06:40:52
senhc
0
Painting

Progress Update : 2021-03-17
Completed
1
nh3pwdmanipur
24.814117127991555,93.93882143497481
24.8110101,93.9385607
0.3464698956359
Approved
2021-03-18 06:41:05
senhc
0
Painting