Progress
 
 
Project Details
DAR-2021-001001
SPT/Senapati HQ Colonies Road/78
Maintenance of Senapati HQ Colonies Road i/c side drain (1.50km) at Senapati HQ.
08/11/2019
PWD
Senapati
48.30
0.00
State Plan
Completed 99%
First
25.269711711188393,94.01926473530426
Shingling, WBM & PC.
Progress Update : 17/03/2021
Completed 99%
First
eesptd
25.269711711188393,94.01926473530426
25.2723283,94.0218166
0.38791897905859
0
Sl. No. Items/Particulars Financial % break-up Physical progress 1. Drain 1 % 0% 2. GSB 26.95% 100% 3. WBM 19.77% 100% 4. PC 52.30% 100%

Progress Update : 17/03/2021
completed 99%
First
eesptd
25.269711711188393,94.01926473530426
25.2646578,94.0183065
0.5701428245249
0
Sl. No. Items/Particulars Financial % break-up Physical progress 1. Drain 1 % 0% 2. GSB 26.95% 100% 3. WBM 19.77% 100% 4. PC 52.30% 100%

Progress Update : 17/03/2021
Completed 99%
First
eesptd
25.269711711188393,94.01926473530426
25.2701529,94.0202211
0.10795168560054
0
Sl. No. Items/Particulars Financial % break-up Physical progress 1. Drain 1 % 0% 2. GSB 26.95% 100% 3. WBM 19.77% 100% 4. PC 52.30% 100%

Progress Update : 15/03/2021
completed 99%
1
eesptd
25.269711711188393,94.01926473530426
25.2606505,94.016073
1.0573945929016
0
Sl. No. Items/Particulars Financial % break-up Physical progress 1. Drain 1 % 0% 2. GSB 26.95% 100% 3. WBM 19.77% 100% 4. PC 52.30% 100%

Progress Update : 15/03/2021
completed 99%
1
eesptd
25.269711711188393,94.01926473530426
25.2639269,94.0179875
0.65590695441766
0
Sl. No. Items/Particulars Financial % break-up Physical progress 1. Drain 1 % 0% 2. GSB 26.95% 100% 3. WBM 19.77% 100% 4. PC 52.30% 100%

Progress Update : 15/03/2021
completed 99%
1
eesptd
25.269711711188393,94.01926473530426
25.2639269,94.0179875
0.65590695441766
0
Sl. No. Items/Particulars Financial % break-up Physical progress 1. Drain 1 % 0% 2. GSB 26.95% 100% 3. WBM 19.77% 100% 4. PC 52.30% 100%