Progress
 
 
Project Details
DAR-2021-000982
KMJ/ Wanglee-Namlee/6
Construction of road from Wanglee to Namlee 5 km.
16/03/2020
PWD
Kamjong
180.00
133
State Plan
completed
Phase 1
24.50192,94.410455
Progress Update : 16/03/2023
completed
Phase 1
je1kamjongdiv
24.50192,94.410455
24.502064,94.4279751
1.7726965588646
133
Rcc ring culvert

Progress Update : 16/03/2023
completed
Phase 1
je1kamjongdiv
24.50192,94.410455
24.502064,94.4279751
1.7726965588646
133
Rcc ring culvert

Progress Update : 16/03/2023
completed
Phase 1
je1kamjongdiv
24.50192,94.410455
24.5049243,94.4092904
0.35421880423267
133
Rcc ring culvert

Progress Update : 16/03/2023
completed
Phase 1
je1kamjongdiv
24.50192,94.410455
24.5019195,94.4104547
9.4930730546311E-5
133
Rcc ring culvert

Progress Update : 15/03/2021
In progress
Phase I
so1ukl
24.50192,94.410455
24.500554,94.4265776
1.6382954923165
40
Construction of road. Earthwork in widening

Progress Update : 15/03/2021
In progress
Phase I
so1ukl
24.50192,94.410455
24.5110676,94.4098304
1.0190789351151
0
Construction of road. Earthwork in widening

Progress Update : 15/03/2021
In progress
Phase I
so1ukl
24.50192,94.410455
24.511126,94.4098071
1.0257079405289
80
Construction of road. Earthwork in widening