Progress
 
 
Project Details
DAR-2021-000943
SPT/Ihilo - Khipo/63
Construction of IVR from Ihilo to Khipo at Makhan 4 km
2020-03-07
PWD
Senapati
100.00
0.00
State Plan
11%
Phase I
25.421072291328464,94.12562656402602
Earth Work, Shingling & Culvert.
Progress Update : 2021-03-17
11%
Phase I
eesptd
25.421072291328464,94.12562656402602
25.4149807,94.100377
2.6246260837162
Approved
2021-03-19 07:37:43
pwdse2ce
0
Sl. No. Items/Particulars Financial % break-up Physical progress 1. Earthwork 45.43 % 25% 2. Drain 1.74 % 0% 3. GSB 30.53% 0% 4. Culvert 22.20 % 0% Overall physical progress = 11%

Progress Update : 2021-03-17
11%
Phase I
eesptd
25.421072291328464,94.12562656402602
25.4165857,94.12627
0.50302974519008
Approved
2021-03-19 07:36:59
pwdse2ce
0
Sl. No. Items/Particulars Financial % break-up Physical progress 1. Earthwork 45.43 % 25% 2. Drain 1.74 % 0% 3. GSB 30.53% 0% 4. Culvert 22.20 % 0% Overall physical progress = 11%

Progress Update : 2021-03-15
11%
1
eesptd
25.421072291328464,94.12562656402602
25.416225,94.1259503
0.53994795369571
Approved
2021-03-19 07:36:04
pwdse2ce
0
Sl. No. Items/Particulars Financial % break-up Physical progress 1. Earthwork 45.43 % 25% 2. Drain 1.74 % 0% 3. GSB 30.53% 0% 4. Culvert 22.20 % 0% Overall physical progress = 11%

Progress Update : 2021-03-15
11%
1
eesptd
25.421072291328464,94.12562656402602
25.416225,94.1259503
0.53994795369571
Approved
2021-03-19 07:35:27
pwdse2ce
0
Sl. No. Items/Particulars Financial % break-up Physical progress 1. Earthwork 45.43 % 25% 2. Drain 1.74 % 0% 3. GSB 30.53% 0% 4. Culvert 22.20 % 0% Overall physical progress = 11%

Progress Update : 2021-03-15
11%
1
eesptd
25.421072291328464,94.12562656402602
25.416225,94.1259503
0.53994795369571
Approved
2021-03-19 07:34:32
pwdse2ce
0
Sl. No. Items/Particulars Financial % break-up Physical progress 1. Earthwork 45.43 % 25% 2. Drain 1.74 % 0% 3. GSB 30.53% 0% 4. Culvert 22.20 % 0% Overall physical progress = 11%

Progress Update : 2021-03-15
11%
1
eesptd
25.421072291328464,94.12562656402602
25.4177033,94.1259503
0.37600490149121
Approved
2021-03-19 07:32:44
pwdse2ce
0
Sl. No. Items/Particulars Financial % break-up Physical progress 1. Earthwork 45.43 % 25% 2. Drain 1.74 % 0% 3. GSB 30.53% 0% 4. Culvert 22.20 % 0% Overall physical progress = 11%

Progress Update : 2021-03-15
11%
1
eesptd
25.421072291328464,94.12562656402602
25.4177033,94.1259503
0.37600490149121
Approved
2021-03-19 07:31:08
pwdse2ce
0
Sl. No. Items/Particulars Financial % break-up Physical progress 1. Earthwork 45.43 % 25% 2. Drain 1.74 % 0% 3. GSB 30.53% 0% 4. Culvert 22.20 % 0% Overall physical progress = 11%

Foundation & Inauguration
-
-
-

-
-
-