Progress
 
 
Project Details
DAR-2021-000939
EE/CDL/Wangoo Lamkhai-Komsen
B/T of road from Wangoo Lamkhai to Komsen 0.0 - 4.0
2020-03-23
PWD
Chandel
60.00
10
State Plan
Work in progress
Phase-1
24.360468,93.89464
Progress Update : 2022-12-16
Work in progress
Phase-1
pashel
24.360468,93.89464
24.3537087,93.8905106
0.86011931767718
Approved
2023-02-02 10:23:50
pwdse2ce
10
WBM layer

Progress Update : 2022-12-09
Work in progress
Phase -I
pashel
24.360468,93.89464
24.3537168,93.8901923
0.87547912480543
Approved
2023-02-02 10:24:32
pwdse2ce
10
WBM layer in progress

Foundation & Inauguration
-
-
-

-
-
-