Progress
 
 
Project Details
DAR-2021-000930
SPT/Little flower School/75
Improvement of road from Katomei Centre to Saizii Little Flower School - 3.00
2020-03-17
PWD
Senapati
45.00
8
State Plan
100%
First
25.27744834405967,94.01685762405434
Shingling, WBM & Culvert.
Progress Update : 2021-03-13
100%
First
eesptd
25.27744834405967,94.01685762405434
25.2740843,94.0116061
0.64707666834449
Approved
2022-12-07 16:18:44
pwdse2ce
8
SL Item Financial break-up Physical progress 1) K. drain 1.64% 50% 2) GSB 35.97% 70% 3) WBM 51.31% 0% 4) Pipe culvert 11.08% 33%

Progress Update : 2021-03-13
100%
First
eesptd
25.27744834405967,94.01685762405434
25.2740843,94.0116061
0.64707666834449
Approved
8
SL Item Financial break-up Physical progress 1) K. drain 1.64% 50% 2) GSB 35.97% 70% 3) WBM 51.31% 0% 4) Pipe culvert 11.08% 33%

Progress Update : 2021-03-13
100%
First
eesptd
25.27744834405967,94.01685762405434
25.2740843,94.0116061
0.64707666834449
Approved
8
SL Item Financial break-up Physical progress 1) K. drain 1.64% 50% 2) GSB 35.97% 70% 3) WBM 51.31% 0% 4) Pipe culvert 11.08% 33%

Progress Update : 2021-03-13
30%
First
eesptd
25.27744834405967,94.01685762405434
25.2740843,94.0116061
0.64707666834449
Approved
2021-03-15 08:06:48
pwdse2ce
0
SL Item Financial break-up Physical progress 1) K. drain 1.64% 50% 2) GSB 35.97% 70% 3) WBM 51.31% 0% 4) Pipe culvert 11.08% 33%

Progress Update : 2021-03-13
30%
First
eesptd
25.27744834405967,94.01685762405434
25.2702135,94.0179875
0.81242141330072
Approved
2021-03-15 08:07:08
pwdse2ce
0
SL Item Financial break-up Physical progress 1) K. drain 1.64% 50% 2) GSB 35.97% 70% 3) WBM 51.31% 0% 4) Pipe culvert 11.08% 33%

Foundation & Inauguration
-
-
-

-
-
-